Use It Now. Pay Nothing. Risk Nothing.

How We Engineered ‘Provisional Go-Live’—a Custom Contract Milestone That Gave the Client Full Access Without Losing Leverage, While Giving the Vendor Time Without Penalties

The Situation

The Situation

During a major automation rollout for a large trans-Tasman retail group, delays from the vendor side pushed the formal go-live milestone beyond the original schedule. The system was largely functional, and the client needed to begin operations to meet peak demand — but doing so would typically trigger milestone payments, risk transfer, and release of liquidated damages claims.

Activating the system too early would mean absorbing commercial risk without final delivery being achieved. On the other hand, leaving the system idle would disrupt the client’s operational ramp-up, resulting in lost value and reputational cost internally.

During a major automation rollout for a large trans-Tasman retail group, delays from the vendor side pushed the formal go-live milestone beyond the original schedule. The system was largely functional, and the client needed to begin operations to meet peak demand — but doing so would typically trigger milestone payments, risk transfer, and release of liquidated damages claims.

Activating the system too early would mean absorbing commercial risk without final delivery being achieved. On the other hand, leaving the system idle would disrupt the client’s operational ramp-up, resulting in lost value and reputational cost internally.

During a major automation rollout for a large trans-Tasman retail group, delays from the vendor side pushed the formal go-live milestone beyond the original schedule. The system was largely functional, and the client needed to begin operations to meet peak demand — but doing so would typically trigger milestone payments, risk transfer, and release of liquidated damages claims.

Activating the system too early would mean absorbing commercial risk without final delivery being achieved. On the other hand, leaving the system idle would disrupt the client’s operational ramp-up, resulting in lost value and reputational cost internally.

Our Role

Our Role

As Superintendent, we recognised the binary structure of traditional go-live clauses wouldn’t serve either party in this case. We designed and implemented a new project milestone — Provisional Go-Live — a contractually recognised middle ground that:

  • Enabled the client to use the system operationally

  • Deferred all formal risk transfer

  • Paused milestone-based payment obligations

  • Maintained liquidated damages exposure

  • Gave the vendor more time to complete rectifications without penalty

This milestone was formally communicated, executed under Superintendent notification, and signed off by both parties. It allowed both sides to decouple beneficial use from commercial finality — creating breathing room, clarity, and preserved leverage.

The Outcome

The Outcome

  • Client gained early operational use of the system — at zero commercial cost

  • Vendor was granted additional time without triggering liquidated damages

  • No risk transferred to the client until all conditions for formal go-live were met

  • The relationship remained intact — avoiding escalation or legal posturing

  • A new best-practice precedent was set for high-pressure automation programs

Governance Without Compromise

Governance Without Compromise

‘Provisional Go-Live’ was not standard practice — it was a strategic invention. Created from a deep understanding of both contract mechanics and real-world operational needs, it delivered flexibility without compromise.

Why It Mattered

Why It Mattered

Most project delays result in one party losing out — either by accepting risk prematurely or by escalating conflict. This solution avoided both. It protected the client’s leverage, gave the vendor fair ground to complete, and ensured operations didn’t grind to a halt. Structured leadership and contractual fluency turned a stalemate into a win-win — with zero downside.

Ready to build with us?

Contact us today to start your project.

Ready to build with us?

Contact us today to start your project.

Ready to build with us?

Contact us today to start your project.

Ready to build with us?

Contact us today to start your project.